Gore Pass Power Line Rebuild: Jun. 30 - Nov. 1
 
About MPEI Link
Billing Link
Energy Efficiency Link
Links Link
Member Benefits Link
Meter and Outage Info Link
Products Link
Safety Link
         Mountain
               Parks
                   Electric
      Mountain
              P
arks
                  E
lectric

Mountain Parks Electric plans to rebuild portions of the 50-plus-year-old overhead distribution line from single-phase to three-phase in order to maintain safe, reliable service to our members in the future.

This line is located in the Gore Pass area. The rebuild begins at Highway 40 and Co Hwy 134 and extends for approximately 8 miles west from the intersection. Equipment will be mobilized into this area commencing June 30. Expected target date for completion is November 1, 2008. Minor outages may occur for brief periods during construction.

MPE wants to thank its members for their support and patience. If there are questions or concerns about this project, please call Gary Billiet at 970-887-3378 or Sam Henderhan at 970-724-3314.

 

back

 

 

 

 

 

MPEI logo

Main Office - 321 West Agate Avenue, PO Box 170, Granby, Colorado 80446-0170

(970) 887-3378 - FAX (970) 887-3996 Denver Metro area - (303) 377-2525

email us    site map
Home Link About MPEI Link Billing Link Energy Efficiency Link Links Link Member Benefits Link Meter and Outage Information Link Safety Link Products Link New Construction Link MPEI Home Page Link